AIMS Attachment A: AIMS Statement of Work
Page 125 of 130
F. Recording:
1. Describe actual operational tests performed and equipment used and
list personnel performing tests.
2. Record in tabular form all test results, deficiencies, and corrective
measures.
G. Termination
1. Performance Verification Testing shall be terminated by the County
when:
i Individual components, subsystems, or the AIMS fail to perform as
specified.
ii It is determined that system is missing components or installation is
not complete.
2. Upon termination, corrective work shall be performed and Performance
Verification Testing rescheduled with the County.
3. Retesting shall be performed by CONTRACTOR at no additional
expense.
4. CONTRACTOR shall continue to perform corrective actions and retest
until system passes all tests to satisfaction of the County.
4.2.4 Endurance Testing
A. CONTRACTOR to provide personnel to monitor the system operation 24
hours per day, including weekends and holidays during endurance testing.
B. Start test after:
1. Successful completion of Performance Verification Testing.
2. Training as specified has been completed.
3. Correction of deficiencies has been completed.
4. Receipt of written start notification from the County.
C. Monitor all systems during Endurance Testing. Coordinate monitoring
with the County.
D. Recording: Record data on approved forms so as to provide a continuous
log of systems performance. Include:
1. Date and time for all entries.
2. Name of individual making entry.
Exhibit 3
Page 185 of 278