16.9 No Damages for Delay.
No claim for damages or any claim, other than for an extension of time, shall be
made or asserted against County by reason of any delays except as provided
herein. Contractor shall not be entitled to an increase in the Contract price or
payment or compensation of any kind from County for direct, indirect,
consequential impact or other costs, expenses or damages, including but not
limited to costs of acceleration or inefficiency, arising because of delay,
disruption, interference or hindrance from any cause whatsoever, whether such
delay, disruption, interference or hindrance be reasonable or unreasonable,
foreseeable or unforeseeable, or avoidable or unavoidable; provided, however,
that this provision shall not preclude recovery of damages by Contractor for
actual delays due solely to fraud, bad faith or active interference on the part of
County or the Consultant or its Contractor Administrator or designee. Otherwise,
Contractor shall be entitled only to extensions of the Contract time as the sole
and exclusive remedy for such resulting delay, in accordance with and to the
extent specifically provided above.
16.10 Excusable Delay; Compensable; Non-Compensable.
16.10.1 Excusable Delay. Delay which extends the completion of the work and
which is caused by circumstances beyond the control of Contractor or its
subcontractors, suppliers or vendors are Excusable Delay. Contractor is
entitled to a time extension of the Contract time for each day the work is
delayed due to Excusable Delay. Contractor shall document its claim for
any time extension as provided in this Article 16. Failure of Contractor to
comply with this Article 16 as to any particular event of delay shall be
deemed conclusively to constitute a waiver, abandonment or
relinquishment of any and all claims resulting from that particular event
of delay. Excusable Delay may be compensable or non-compensable:
16.10.2 Compensable Excusable Delay. Excusable Delay is compensable
when (i) the delay extends the Contract time, (ii) is caused by
circumstances beyond the control of the Contractor or its subcontractors,
suppliers or vendors, and (iii) is caused solely by fraud, bad faith or
active interference on the part of County or its agents. In no event shall
Contractor be compensated for interim delays which do not extend the
Contract time. Contractor shall be entitled to its direct costs for
Compensable Excusable Delay. Direct costs recoverable by Contractor
shall be limited to its actual additional costs.
16.10.3 Non-Compensable Excusable Delay When Excusable Delay is
(i) caused by circumstances beyond the control of Contractor, its
subcontractors, suppliers and vendors, and is also caused by
circumstances beyond the control of the County or its Consultant, or
Contract Administrator or designee or (ii) is caused jointly or concurrently