AIMS Attachment A: AIMS Statement of Work
Page 127 of 130
ii CONTRACTOR to make no repairs during this phase unless
authorized in writing by the County.
4. Step IV - Final Assessment:
i After successful completion of Step I, conclusion of Step III, or
termination of testing, CONTRACTOR to identify all failures,
determine causes, and repair. Submit explaining the nature of
each failure, corrective action taken, results of tests performed, and
recommended point for resumption of testing.
ii After submission of report schedule review meeting at job site.
CONTRACTOR to schedule date and time with the County.
iii At review meeting, demonstrate that all failures have been
corrected by performing Performance Verification Testing.
iv Based on report and review meeting, the County will approve
endurance test or direct CONTRACTOR to repeat all or part of
Steps III and IV.
4.2.5 Adjustment, Correction, and Maintenance
A. During Endurance Testing CONTRACTOR is to make adjustments and
corrections to system only after obtaining written approval of the County.
B. During Endurance Testing, CONTRACTOR is to perform required
maintenance on systems including provision of replacement parts.
4.2.6 Final Inspection
A. After Endurance Testing is complete, review tabulated records with the
County.
B. The CONTRACTOR will not be responsible for failures caused by:
1. Outage of main power in excess of backup power capability provided
that automatic initiation of all backup sources was accomplished and
automatic shutdowns and restarts of systems performed as specified.
2. Failure of any County furnished power, communications, and control
circuits provided failure was not due to CONTRACTOR furnished
equipment, installation, or software.
3. Failure of existing County equipment provided failure was not due to
CONTRACTOR furnished equipment, installation, or software.
C. When performance of AIMS does not fall within the above rates,
CONTRACTOR shall determine cause of deficiencies, correct, and retest.
Exhibit 3
Page 187 of 278