AIMS Attachment A: AIMS Statement of Work
Page 36 of 130
be attended by the personnel who will perform the work and a
representative of the County. Each preparatory inspection meeting shall
include:
1. A review of the project requirements, including applicable code
requirements. The purpose is to make sure the people actually doing
the work clearly understand the level of quality required.
2. A check to assure that all materials and equipment have been tested,
submitted and approved.
3. A check to assure that provisions to provide required control testing
have been made.
4. Examination of the work area to ascertain that all preliminary work has
been completed.
5. A physical examination of materials and equipment to assure that they
conform to approved shop drawings or submittal data and that all
materials and equipment are on hand and properly stored.
B. Initial Inspections - CONTRACTOR shall perform an initial inspection as
soon as a representative portion of the particular feature of work is started
and such inspection shall include:
1. An examination of the quality of workmanship.
2. A review of control testing for compliance with Contract requirements.
3. An inspection to make sure there is no use of defective or damaged
materials, omissions and dimensional requirements.
C. Follow-up Inspections - CONTRACTOR shall perform daily follow-up
inspections to assure continuing compliance with Contract requirements,
including control testing, until completion of the particular feature of work.
2.3.4 Quality Control Plan - The CONTRACTOR shall furnish a Quality Control
Plan to the County prior to the Pre-Installation Conference. The Quality
Control Plan shall be updated as required. The Quality Control Plan shall
include the personnel, procedures, instructions and records to be used. The
Quality Control Plan shall include as a minimum:
A. Organization - A description of the CONTRACTOR‟s Quality Control
Organization, including: An organization chart showing lines of authority
and relationship of the Quality Control Organization to other
CONTRACTOR management and project personnel; names and
qualifications of personnel in the Quality Control Organization; area of
responsibility; and authority of each individual in the Quality Control
Organization.